The tunnel reduces the travel time and overall distance between
Manali and
Keylong on the way to
Leh. The route, which previously went through Gramphu, was 116 km (72.1 mi) long and took 5 to 6 hours in good conditions. A traveller now reaches the South Portal of the tunnel from
Manali, a distance of 24.4 km (15.2 mi) in about 45 minutes, goes through the 9.02 km (5.6 mi) long tunnel in about 15 minutes, and reaches
Keylong which is 37 km (23.0 mi) away in about 60 minutes. The new route via the tunnel brings down the total distance travelled to 71 km (44.1 mi) which can be covered in about 2 hours, a reduction of around 3 to 4 hours when compared to the earlier route. Moreover, the tunnel bypasses most of the sites that were prone to road blockades, avalanches, and traffic snarls.[8][9]
The tunnel is at an elevation of 3,100 metres (10,171 ft) whereas the Rohtang Pass is at an elevation of 3,978 metres (13,051 ft). It was inaugurated by
Prime MinisterNarendra Modi on 3 October 2020. The cost of the entire project is ₹3,200
crore (US$438 million).[10] The tunnel was completed by the
Border Roads Organisation (
BRO) under Ministry of Defence. The tunnel can be visited by citizens and students of the nation. It will also boost
tourism in Himachal.
History
In 19th Century
The Moravian Mission first talked about the possibility of a tunnel through Rohtang Pass to reach Lahaul in 1860.[11]
In 20th Century
The proposal for the construction of a tunnel across Rohtang Pass was first conceived in 1942 by Dr.
John Bicknell Auden,
Geological Survey of India (GSI) who at that time visited this pass intending to divert the water of Chandra river to Beas.[11]
When
Atal Bihari Vajpayee became the Prime Minister, locals suggested his childhood friend Arjun Gopal, To visit him and to talk about Rohtang Tunnel. Gopal and two companions,
Chhering Dorje and Abhay Chand, moved to
Delhi. After a year of discussions, Vajpayee went to
Lahaul in June 2000 and declared that the Rohtang Tunnel would be constructed.[12]RITES conducted a feasibility study.
In 2000, the project was estimated to cost ₹500 crore and be completed in seven years.[13] On 26 May 2002, the
Border Roads Organisation (BRO), a tri-service organisation of the
Defence Ministry specialising in road and bridge construction in difficult terrains, headed by Lt. Gen. Prakash Suri, PVSM, was put in charge of construction.[14] The approach road to the tunnel entrance was inaugurated by
Atal Bihari Vajpayee.
However the project did not move beyond the tree-felling stage by May 2003. By December 2004, the cost estimate had grown to ₹900 crore.[15] In May 2007, the government of
Dr. Manmohan Singh awarded the contract to
SMEC (Snowy Mountains Engineering Corporation) International Private Limited, an Australian company, and the completion date was revised to 2014. However, there was no progress for the next three years, until May 2010.[16]
Finally, the
Cabinet Committee on Security in UPA government cleared the Rohtang Tunnel Project. The work was awarded to a joint venture of
AFCONS Infrastructure Limited, an Indian construction company of
Shapoorji Pallonji Group, and
STRABAG AG, Austria, in September 2009.[17] The drilling of the Rohtang Tunnel through the Himalayan ranges began on 28 June 2010 at the South Portal, 25 km (16 mi) north of
Manali. Some of the anchoring and slope stabilisation work was subcontracted to Spar Geo Infra Pvt Ltd. Permanent maintenance free earthing system design, supply and installation was sub-contracted to Manav Energy Pvt. Ltd.[18]
Prime Minister
Narendra Modi renamed the tunnel as the Atal Tunnel, in honour of Shree Atal Bihari Vajpayee, on 25 December 2019, Vajpayee's birthday.[12]
The Atal Tunnel has been planned to ensure an all-seasons, all-weather road route to strategically important areas of
Ladakh and the remote
Lahaul-Spiti valley. However, the tunnel will provide this connectivity only up to
Darcha, north of Keylong in the Lahaul region of
Himachal Pradesh. Connectivity to Ladakh will require more tunnels: either at Shikun La, or at the passes located on the present Leh-Manali road. Director General Border Roads Lt Gen Rajeev Chaudhry, VSM has initiated plans for construction of tunnel at Shinkula.
Timeline
Total length of tunnel is 9.02 km.
The project was announced by the then Prime Minister
Atal Bihari Vajpayee on 3 June 2000. The work was entrusted to
BRO on 6 May 2002.[19]
As of June 2012, two years after the start of the project, 3.5 km of the tunnel digging had been completed.[20]
Only a little progress was made in the next one year due to heavy ingress of water at serri nullah fault zone, that required constant dewatering and slowed the digging and blasting to a crawl.
As of October 2013, a little more than 4 km of the tunnel had been dug. However, about 30 m portion of the roof of the tunnel collapsed towards the north portal on 17 October 2013 and the digging had to be stopped.[21]
As of September 2014, 4.4 km of the tunnel, i.e., half of 8.8 km planned length had been dug.[22][23]
As of December 2016, 7.6 km of the tunnel digging had been completed. Excavation was expected to be completed in 2017, with opening in the second half of 2019.[24][25]
As on 22 November 2017, it was decided to allow patients to be carried through the under-construction tunnel only in the gravest of emergency when the helicopter service was not available and not to allow civilians to enter the tunnel before completion due to risks of falling rocks, lack of oxygen in the tunnel as ventilation system was yet to be installed, etc. and likely interruption in construction work due to presence of civilians.[28]
Sep 2018: the tunnel was used for evacuation of people stranded in Lahaul after sudden spell of bad weather blocked Rohtang La due to snowfall.[29]
Nov 2019: Bus service trial started through the yet-incomplete tunnel on 17 November 2019.[30] A
Himachal Road Transport Corporation bus carrying 44 passengers entered tunnel from the south portal and the passengers alighted at the north portal. The bus service operated for next five winter months for residents of Lahaul and Spiti valleys. Private vehicles were not allowed through the tunnel.[31]
Dec 2019: On 25 December the tunnel, which was known as Rohtang tunnel till then, was officially renamed as the Atal Tunnel.
Mar 22 : Minister of Defence
Shri Rajnath Singh dedicated website
https://marvels.bro.gov.in dedicated to the Nation which will felicitate Citizens and students across the Country to visit the Tunnel.
Challenges
The most challenging task was to continue the excavation during heavy snowfall in winter. Excavation for tunnelling was done from both ends. However, as Rohtang pass closes during the winter, the north portal was not accessible during winter and the excavation was being done only from the south portal in winters. Only about one-fourth of the entire tunnel was excavated from the north end and three-fourths was excavated from the south end. There were more than 46 avalanche sites on approaches to the tunnel.[32]
Other challenges to the progress of the tunnel included difficulties in disposing more than 8
lakh m³ of excavated rock and soil,[33] heavy ingress of water (as much as 30 lakh litres per day in June 2012) that required constant dewatering, costlier treatment and slowed the progress of excavation from 5-metre per day to just half a metre a day and unstable rocks that slowed blasting and digging.[34] A cloud-burst and flash flood on 8 August 2003 killed 42 labourers who were building the temporary access road.[35] Questions were also raised on the impact of cutting down more than 700 trees on the ecology.[36]
Specifications
The tunnel is intended to create an all-weather route to Leh and Lahaul and Spiti valleys in Himachal Pradesh.
Salient features of the Atal Tunnel are as follows:
Length: 9.02 km (5.6 mi)
Shape (cross-section) of Tunnel: Horseshoe
Finished width: 10.00 m (32.8 ft) at road level. (8m pavement and 1m footpath on both sides)
General altitude of the tunnel: 3,000–3,100 m or 9,840–10,170 ft
Designated vehicular speed: 80 km/h (50 mph)
Geology of tunnelling media: Uniformly dipping alternate sequence of quartzites, quartzitic schists, quartz-diolite-schist with thin bands.
Tunnel boring machines were not used because of the inability to see inside the mountain, instead blasting and digging used to build the tunnel.[37]
Temperature variation in the area: 25–30 °C (77–86 °F) during May–June, −30 to −20 °C (−22 to −4 °F) during Dec–Jan.
Overburden: Maximum 1,900 metres (6,230 ft), average more than 600 m (1,970 ft)
Support system: Fibre-reinforced concrete (100–300mm or 0–10 inch thick) combined with rock bolt (26.50mm dia, 5,000–9,000mm or 200–350 inch long) has been used as the principal support system.
Tunnel ventilation: Semi-transverse system of ventilation.
A 2.25 m high and 3.6 m wide emergency tunnel is integrated in the tunnel cross-section beneath the main carriageway.
The following parameters have been set in design:
(a) Upper tolerance limit for concentration – 150ppm
The tunnel was built using the
New Austrian tunnelling method and has been equipped with a semi-transverse ventilation system, where large fans separately circulate air throughout the tunnel. A 2.250 m tall and 3.6 m wide emergency tunnel has been integrated into the tunnel cross-section beneath the main carriageway for evacuation during emergencies.
Fires inside the tunnel will be controlled within an area of 200 metres and fire hydrants are provided at specific locations throughout the tunnel. The tunnel also has a public announcement system to make important announcements in emergency situations for which loudspeakers are installed at regular intervals.
Heavy snowfall in the
Rohtang Pass area is a major concern, especially on the approach roads to the main tunnel. To prevent any damage to the roads and to ensure the safety of the roads and tunnel users alike, avalanche control structures have been constructed. Since the Atal tunnel is likely to witness heavy traffic, CCTV cameras are placed at regular intervals in the tunnel which are connected to two monitoring rooms on both ends of the tunnel for vehicular management and pollution monitoring. Pollution sensors continuously monitor the air quality in the tunnel and if the air quality in the tunnel is below the desired level, fresh air is injected into the tunnel via two heavy duty fans on each side of the tunnel.
Gallery
Prime Minister
Narendra Modi and other dignitaries after the inauguration of the Atal Tunnel.
Prime Minister
Narendra Modi is walking through the roads of the tunnel after its inauguration.
Prime Minister
Narendra Modi flags off a bus from
Manali after inaugurating the Atal Tunnel.
Trivia
The 9.02 km (5.6 mi) long tunnel is presently the world's longest single tube highway tunnel at an altitude above 3,000 m(10,000 ft). There are some railway tunnels like 32.645 km long
New Guaijiao Railroad Tunnel at 3,300 meters above the sea level in China. Higher but shorter tunnels in China include the 7.1 kilometer Que'ershan Tunnel (雀儿山隧道) at 4378 meters and the 5.7 kilometer Milashan Tunnel (米拉山隧道) at 4774 meters . The nearest in comparison to the Rohtang Tunnel is the 8.8 kilometer Zhegushan Tunnel (鹧鸪山隧道), altitude 3,200 metres (10,500 ft)).[39][circular reference]Salang Tunnel in the
Hindu Kush mountains in
Afghanistan (length 2.6 km, altitude 3,400m) and the
Eisenhower–Johnson Memorial Tunnel in United States (length 2.73 km (1.7 mi), altitude 3,401 m (11,158 ft))are also at 3000+ meters .
After frequent visits of Director General Border Roads, officials from Defence Ministry and Himachal Chief Minister
Jai Ram Thakur, 31 August 2020 was the deadline set to complete the remaining works in the tunnel. Started on 28 June 2010, the Atal Tunnel was inaugurated by the Prime Minister,
Narendra Modi 3 October 2020.[41]