Atatürk Airport was one of the busiest airports in Europe. Since 2013, it had ranked among the five busiest airports in Europe by passenger traffic. In 2017, Atatürk Airport and
Sabiha Gökçen, Istanbul's other international airport, handled over 100 million passengers combined.[11] By comparison, the six London-area airports
serve more than 150 million passengers a year, while the three Paris-area airports
serve around 100 million passengers a year.
As Atatürk Airport was hemmed in by the city on three sides and the sea of Marmara on another, it was unable to expand to meet the growing demands placed on it. Sabiha Gökçen was also at capacity. The decision was taken to build a new airport, well away from the city to ensure ample space.
Location
It was decided to construct the new airport at the intersection of roads to
Arnavutköy,
Göktürk, and
Çatalca, north of central Istanbul and between the
Black Sea coast towns of
Yeniköy [
tr],
Tayakadın and Akpınar. The area is a 7,600-hectare (19,000-acre) region near
Lake Terkos. Some 6,172 hectares (15,250 acres) of this area was state-owned forest. The distance between Istanbul Airport and Atatürk Airport is approximately 35 km (22 mi). The area encompassed old
open-pit coal mines, which were later filled with soil.[12]
According to the Environmental Impact Assessment (ÇED) report published in April 2013, there were a total of 2,513,341 trees in the area and 657,950 of them would need to be cut indispensably, while 1,855,391 trees would be moved to new places. However, the
Ministry of Forest and Water Management claimed the exact number of trees cut and moved would only be revealed after construction was complete.[12]
Construction
Construction of the airport was divided over four phases. When all stages are completed, the airport will have the capacity to serve 200 million yearly passengers, which would at that time have made it the world's biggest airport. The cost of the project was estimated at €7 billion, without accounting for the cost of financing.
The project was achieved by an international design team working across different phases, but all focused on the collective vision.
The architects behind the concept design were
Grimshaw Architects,
Nordic Office of Architecture and
Haptic Architects.
The lead delivery architect was Scott Brownrigg, also in charge of the interior concept design with IGA Design. Local delivery architects were Fonksiyon Mimarlik, Turgut Alton Mimarlik and Kiklop Design & Engineering.[13]
A tender was made for the construction as well as for operating the airport. Bidding for these tenders took place on 3 May 2013. Of the eligible companies, four Turkish and two foreign contenders took part in the bidding process. The Turkish joint venture consortium of
Cengiz-Kolin-
Limak-Mapa-
Kalyon won the tender and were obliged to pay the government
€26.142 billion including
value-added tax for a 25-year lease starting from 2018. The completion date of the construction's first stage was officially set for 2018 – 42 months after the finalization of the tender's approval.[12]
The groundbreaking ceremony took place on 7 June 2014,[14] though construction only started in May 2015 after the land was officially handed over.[15]
The inauguration of the airport took place on the planned date of 29 October 2018. It was reported that the first test landing at the airport would take place on 26 February 2018; however, the first landing took place on 20 June 2018.[16] Testing of navigational and electronic systems with
DHMİ aircraft had begun on 15 May 2018.[17]
The control tower is in the shape of the Turkish national flower, the
tulip.[18]
Project stages
The construction of the airport is taking place in several stages, expanding the airport and its facilities over time.[19][20][21]
The first stage consists of the main terminal, with an annual passenger capacity of 90 million and an area of 1,440,000 m2 (15,500,000 sq ft) — making it the world's
third-largest airport terminal building.[22] There will also be two pairs of parallel
runways connected to eight parallel
taxiways to the west of the main terminal, approximately 4,000,000 m2 (43,000,000 sq ft) of apron space, and an indoor
car-park with a capacity of 12,000 vehicles. In addition, the airport will feature three technical blocks for repairs, maintenance, and fueling, as well as an
air traffic control tower, eight ramp control towers, and hangars for cargo and
general aviation aircraft.[23] Several other services are also to be in operation, including hospitals, frequent-flyer and VIP lounges, prayer rooms, convention centers, and hotels; some of these are expected to form part of the Istanbul Airport City project.[24]
The second stage will add a third independent runway to the east of the main terminal, as well as a fourth remote runway with an east–west heading and additional taxiways and apron areas. The third stage is planned to add a second passenger terminal with a capacity of 60 million annual passengers and an estimated area of around 960,000 m2 (10,300,000 sq ft), as well as an additional runway and new support facilities area.
The fourth and final stage of expansion will, along with adding another runway, allow for the construction of
satellite terminals with a combined capacity of 50 million passengers and an area of up to 800,000 m2 (8,600,000 sq ft) if needed.[23]
Once fully completed by 2027, the airport will have six sets of runways (eight in total), 16 taxiways, and a total annual passenger capacity of 150 million passengers.[22][25] If fully expanded to a capacity of 200 million, the airport will exhibit four terminal buildings with interconnecting rail access that combine for a total indoor area of 3,200,000 m2 (34,000,000 sq ft). The airport will also have a 6,500,000 m2 (70,000,000 sq ft) apron with a parking capacity of 500 aircraft, VIP lounges, cargo and general aviation facilities, a state palace, and indoor and outdoor parking that can accommodate up to 70,000 cars. A medical center,
aircraft rescue and firefighting stations, hotels, convention centers, power plants, and
wastewater treatment facilities will also be built.
Controversies
The Turkish Chamber of Environmental Engineers (ÇMO) took the project tender to court on the grounds that the project violated the existing legislation for the preparation of the Environmental Impact Assessment (ÇED) report.[12] In February 2014, an Istanbul administrative court ordered the construction of the airport to be suspended.[26] However, the groundbreaking ceremony still took place a few months later, on 7 June 2014.[14]
A report published in the Turkish newspaper Cumhuriyet in February 2018 claimed that more than 400 workers had been killed during the construction of the airport, with accidents killing three to four workers every week, and families of the killed workers being paid to remain silent about the incidents.[27][28] Turkish daily Evrensel also alleged that fatal accidents continued to occur.[28] This prompted
opposition MPVeli Ağbaba to submit a written questionnaire to the
Turkish parliament on 13 February 2018. In response, the
Turkish Ministry of Labour and Social Security claimed that there were only 27 fatalities during the construction of the airport.[29] In October 2019, UK publications Construction News and Architects' Journal published a joint investigation into fatalities at the airport, nicknamed by workers "the cemetery" as so many have died. By this point, the official death toll had risen to 55, but unofficial estimates suggested that the figure could be "higher than 400".[13]
Mass worker protests broke out on 14 September 2018 after a bus carrying workers crashed, injuring 17. Complaints by workers included poor living conditions in "vermin-infested dormitories", issues in transportation that had left them stranded under the rain or on-site during holidays, and long delays in payments, among others.[30]
Operations
The opening ceremony took place on 29 October 2018, scheduled so as to coincide with the 95th
anniversary of the proclamation of the Turkish Republic.[31] The airport had been unofficially known as 'Istanbul New Airport' during construction – the new official name of 'Istanbul Airport' was announced at the opening ceremony. The first flight from the airport was
Turkish Airlines flight TK2124 to the Turkish capital
Ankara on 31 October 2018.[32] On 1 November 2018, five daily flights began to arrive and depart from the airport: from
Ankara,
Antalya,
Baku,
North Nicosia, and
İzmir,[33] followed by
Adana and
Trabzon starting in December.
Before the full transfer, all flights were operated exclusively by
Turkish Airlines. Regularly scheduled flights to all of the new airport's destinations continued to depart from Atatürk and Sabiha Gökçen airports alongside these trial flights. It was originally planned that on 31 December 2018, all equipment from Atatürk Airport would be transferred to the new airport via the O-7 motorway.[34][35] As of 17 January 2019, the transfer phase was set to start 1 March 2019.[36] However, on 25 February, the transfer phase was moved a fourth time to 5 April 2019.[37]
The full transfer of all scheduled
commercial passenger flights from
Atatürk Airport to the new Istanbul Airport took place on 6 April 2019 between 02:00 and 14:00. Hundreds of trucks carried more than 10,000 pieces of equipment, each weighing about 44 tons were moved to the new airport over 41 hours.[38] Atatürk Airport's
IATA code IST was also transferred to the new airport.
In February 2022,
Turkish Cargo relocated all cargo flights and operations from their former base at Atatürk Airport to the new airport.[39]
Facilities
Runways
The airport currently has one terminal in service for domestic and international flights and five runways (three main and two backups) that are currently in operation. The two 17/35 runways are both 4,100 metres (13,500 feet) long, while the 16/34 runways are both 3,750 metres (12,300 feet) long. Runway 18/36 is 3,060 metres (10,040 feet) long, shorter than the other runways, although it is projected to expand to 3,750 metres (12,300 feet), the same length as the 16/34 pair. Runways 17L/35R and 16R/34L are 60 metres (200 feet) wide, while 17R/35L, 16L/34R and 18/36 are 45 metres (148 feet) wide. All runway surfaces are
asphalt.[40]
Concourses
The airport features a total of five concourses lettered A, B, D, F, and G with a total of 143 passenger boarding bridges. Concourse G, which is located in the southeast, is reserved solely for domestic flights. Three passenger boarding bridges of Concourse F which is directly to the north of Concourse G have also been allocated for domestic flights. Concourses A, B, D, and F are used for international flights. The C and E concourses connect directly to the main terminal and are therefore not independent concourses.[41]
Ali Kuşçu Mosque, which lies within Airport City to the south of the airport and can accommodate up to 6,000 worshippers, has become the world's first "LEED Gold" certified mosque registered with the
U.S. Green Building Council.[44][45]
Airlines and destinations
Passenger
The following airlines operate regular scheduled and charter flights at Istanbul Airport:
^1 : 2018 statistics correspond to the last 3 months of 2018 since the opening of the airport.
Environmental impact
The airport is estimated by
Climate Trace to have emitted the equivalent of almost 9 million tonnes of CO2 in 2022, making it the country's second largest
greenhouse gas emitter.[213]
The M11 metro line was opened on 22 January 2023. The
Gayrettepe extension of the line was put into service on January 29, 2024. Trains run to
Gayrettepe, skipping the
Terminal 2 station. Extension to
Halkalı on the Marmaray rail line is under construction.[214]
Bus
The airport is serviced from the city by public
IETT[215] and Havaist[216] buses.
Car and taxi
The airport is reachable by car from the O-7motorway and/or D.020highway. Istanbul city taxis are available 24 hours a day outside the arrival and departure areas of the airport. A trip to Istanbul city centre by taxi takes approximately an hour.[217]
Rail
There are plans for mainline railway to connect the airport to Çatalca and Halkalı, and via outer city bypass running over the
Yavuz Sultan Selim Bridge across the Bosporus and connecting with the Anatolian rail network at Gebze but construction has been continuously delayed.[218][219]
Accidents and incidents
On 8 May 2024, a
Boeing 767 cargo aircraft belonging to
FedEx made an emergency landing on one of the airport's runways after its front landing gear failed, resulting in its nose dipping into the ground and the temporary closure of the runway.[220]
^"Turkish Airlines is switching to a new Istanbul airport – all in 45 hours". Guardian. 6 April 2019. Retrieved 13 April 2019. The opening date has been pushed back three times, but authorities insist that the main terminal building and two runways will be fully operational by Sunday, in what critics say it is a rushed and dangerous attempt to stay on schedule.
^"Top 10 busiest airports in the world shift with the rise of international air travel demand Revealed". ACI World. 14 April 2024. Retrieved 14 April 2024. The global total passenger forecast for 2023 stands close to 8.5 billion, reflecting a remarkable recovery of 93.8% from pre-pandemic levels. Notably, international traffic recovery drew nearer to that of domestic traffic, emphasizing its essential role in propelling the industry's resurgence and expansion.